Question: Based on the precedence table below, identify the critical path, the earliest start and finish, and the slack for each task. table [ [

Based on the precedence table below, identify the critical path, the earliest start and finish, and the slack for each task.
\table[[Activity,\table[[Duration],[(Days)]],\table[[Immediate],[Predecessor]]],[A,2,None],[B,3,None],[C,4,None],[D,5,A],[E,3,B],[F,7,C],[G,2,D, E],[H,4,F],[I,3,F],[K,1,H],[K,3,I],[L,1,G, J, K]]
Click here for the Excel Data File
a. Identify the critical path.
b-1. Identify the earliest start and finish.
b-2. Identify the slack for each task.
Complete this question by entering your answers in the tabs below.
Req B2
Identify the critical path.
\table[[A-D-G-L],[C-F-I-K-L],[C-F-H-J-L]]
 Based on the precedence table below, identify the critical path, the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!