Question: Based on the predecessor table below, 1) complete the network diagram with E5, EF, LS, LF dates, and oat for each activity and 2) identify

Based on the predecessor table below, 1) complete the network diagram with E5, EF, LS, LF dates, and oat for each activity and 2) identify the project' 5 critical path. Follow the network diagram format that we used in class. A None 2 Dene scope B Document requirements A 3 C Analyze 8: design prototype B 8 D Buy materials (2 3 E Build prototype C 6 F Implement prototype D. E 5 G Teet prototype F 4 H Present prototype to customer G 2 Legend 1. Forward pass: determine ES, EF 2. Backward pass: determine LS, LF 3. Calculate float/slack & identify critical path 0 Float = LS ES itEE The critical path is: ' length of the critical path is days
Step by Step Solution
There are 3 Steps involved in it