Question: Based on the probability and projected costs (INR) shown in the Figure, which 10 decision (build/buy/reuse/contract) should be taken to minimize the overall cost

Based on the probability and projected costs (INR) shown in the Figure,

Based on the probability and projected costs (INR) shown in the Figure, which 10 decision (build/buy/reuse/contract) should be taken to minimize the overall cost of the Software X. Page 1 of 2 No Changes (0.80) 1000 Minor Changes" (0.20) (0.70) 1500 -Major 2000 (0.30) Contract -Changes (0.10)- 8000 Buy No Changes (0.90) 9000 System X 2000 Build Minor (0.30) -Major (0.70)- 4000 Reuse Simple (0.50)- 2000 Major (0.30) Difficult (0.50) 5000 Minor (0.70) 1000