Question: BASED ON THE REPORT BELOW LINK https://www.anao.gov.au/sites/default/files/Auditor-General_Report_2021-2022_13_PDSS_Short_Range_Ground_Based_Air_Defence.pdf based from above supplementary information and case study please answer the how do you write PROJECT ACTIVITY REVIEW
BASED ON THE REPORT BELOW LINK https://www.anao.gov.au/sites/default/files/Auditor-General_Report_2021-2022_13_PDSS_Short_Range_Ground_Based_Air_Defence.pdf based from above supplementary information and case study please answer the how do you write PROJECT ACTIVITY REVIEW for above case study..apa7 rerernces Supplementary Information Proj6003 Short Range Ground Based Air Defense.
Schedule Supplement
1. Project Change Date: 30/6/2021 (Use local Subject Matter Expert Testers)
2. Project Change Process Commencement Date: 1/7/2021
a) Consider and draft Project Change Request: 3/7/2021
b) Received by Project Management Team (PMT): 4/7/2021
c) Reviewed by PMT: 5- 6/7/2021
d) Request Impact Assessment: 7/7/2021
e) Review Impact Statement: 15/7/2021
f) Submit for Approval to the Change Control Board (CCB): 17/7/2021
g) Change Approval with conditions: 20/7/2021
h) Notification of result to all Stakeholders: 22 - 24/7/2021
3. Adjustment to Project Management Plan Baselines: 25/7/2021
4. Testing to take place to bring the project into Project Parameters using Local SME Inspectors: Seek and train SMEs 26/7/2022 - 3/2/2023
5. Initial Material Release (IMR) and Testing: 4/2/2022 - 4/6/2023
6. Initial Operational Capability (IOC) Readiness: 5/6/2023 - 30/6/2023
7. Final Material Release (FMR): 15/10/2025
8. Final Operational Capability (FOC) : 30/6/2026