Question: Based on the table below: ( 1 0 marks ) a . Create a GANTT chart. b . Conduct both a forward and backward pass
Based on the table below: marks
a Create a GANTT chart.
b Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
c Identify all paths through the network. Which is the critical path?
d Which activities have slack time?
e Identify all burst activities and merge activities.
Activity Predecessors Duration Days
A None
B A FS
C A SS
D A
E C SS
F B
G E FF
H E F
I D
J G H I