Question: Based on the table below, how many days will it take to complete the project if Activity E finishes on day 11? Activity Duration IPA
Based on the table below, how many days will it take to complete the project if Activity E finishes on day 11? Activity Duration IPA A 2 none B 3 A C 2 A D 5 B, C E 3 C F 2 D E, A.10 B.12 C.13 D.17