Question: Based on your worksheet calculations, answer the questions below. Question 4a The critical path(s) 1346712457134571367124671257 The project duration is weeks. Question 4b (On Crash options,
Based on your worksheet calculations, answer the questions below. Question 4a The critical path(s) 1346712457134571367124671257 The project duration is weeks. Question 4b (On Crash options, only select those which are actually available.) Crash 1 Options (Uncheck every box to remove the question mark and then check all that apply.) 12 ? 13 ? 24 ? 25 ? 3-4 ? 36 2 ? 4 ? 4-6 ? 57 6-7