Question: Based upon Booked Orders and Sales Predictions, we expect to need the following finished goods over the planning period: 150 Product A We currently have
Based upon Booked Orders and Sales Predictions, we expect to need the following finished goods over the planning period: 150 Product A We currently have the following Finished Goods Products in Inventory: 90 Product A We have scheduled the following to be produced in the factory within the planning period: 20 Product A How many products should we include on future Planned Production Orders?