Question: BASIC INFORMATION: A three-year project will cost $60,000 to construct. This will be depreciated straight-line to zero over the three-year life. The price per unit
BASIC INFORMATION: A three-year project will cost $60,000 to construct. This will be depreciated straight-line to zero over the three-year life. The price per unit sold is $20 and the variable cost per unit sold is $10. Fixed costs are $30,000 per year. In addition to the BASIC INFORMATION, you find that a salvage company will pay you $10,000 for the assets at the end of year 3. The project will require an investment of $10,000 up front for net working capital. If you expect to sell 7,000 units per year, compute the NPV assuming a required return of 15% and a tax rate of 30%. A. Less than $0 B. $11,347 C. $14,416 D. $18,807 E. More than $20,000
The answer is D, please show all the steps, thanks!
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts