Question: BE 3 . 1 3 - Using Excel with Learning Curves PROBLEM Willem was reviewing his former colleague's calculation for unit production time with a

BE3.13- Using Excel with Learning Curves
PROBLEM
Willem was reviewing his former colleague's calculation for unit production time with a learning curve, but he felt like he was missing something. Estimates of the time it would take to make each successive unit and the learning curve observed are provided here.
Expected time to make third unit
Expected time to make fourth unit
Learning curve observed
33.85 minutes
32.40 minutes
90%