Question: BE 4 . 1 ( LO 1 ) Put the data analysis project plan components in their proper sequential order, starting with number 1 for

BE 4.1(LO 1) Put the data analysis project plan components in their proper sequential order, starting with number 1 for the first step.
___ a. Embed controls.
___ b. Identify project objective and specific questions.
___ c. Design data strategy.
___ d. Consider risks.
___ e. Design analysis strategy.