Question: Beck Construction Co. agreed to construct a warehouse for Vaughn Co. for a contract price of $1,200,000. Construction began in x1 and was completed in

Beck Construction Co. agreed to construct a warehouse for Vaughn Co. for a contract price of $1,200,000. Construction began in x1 and was completed in x3. Information related to costs and billings on these contract are as follows: 20x1 20x2 20x3 Costs incurred to date $200,000 $750,000 $900,000 Estimated costs to complete $600,000 $150,000 -0- Customer billings to date $300,000 $950,000 $1,200,000 Collections on billings to date $220,000 $890,000 $1,200,000 Make the required journal entries for x1 and x2 using the percentage of completion method and determine the amount of profit recognized in x3.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!