Question: Before the project started, jack had could not work on the project. John will have to do both of the work. his part and jack

Before the project started, jack had could not work on the project. John will have to do both of the work. his part and jack part. JOhn is now responsible for tasks 3,4,6, and 7.
How will you level the Gantt chart?
what is the new estimated completed time?
2. They hire two more EMPLOYEE to do Jack tasks, reducing the time of the tasks by 50% (4 days becomes 2 days). What will be the new project completion time?
1 2 3 jack john jack john 4 4 days 3 days 4 days 4 days 5 days 3 days 2 days 4 days Wed 11/3/21 Mon 11/8/21 Tue 11/9/21 Thu 11/11/2: 1 Tue 11/9/21 Fri 11/12/21 1 Tue 11/9/21 Fri 11/12/21 1 Mon 11/15/2 Fri 11/19/21 3,2 Mon 11/15/2 Wed 11/17/2 2,3 Thu 11/18/2: Fri 11/19/21 6 Mon 11/22/2 Thu 11/25/2: 5,6 5 6 jack jack john 7 john 8 1 2 3 jack john jack john 4 4 days 3 days 4 days 4 days 5 days 3 days 2 days 4 days Wed 11/3/21 Mon 11/8/21 Tue 11/9/21 Thu 11/11/2: 1 Tue 11/9/21 Fri 11/12/21 1 Tue 11/9/21 Fri 11/12/21 1 Mon 11/15/2 Fri 11/19/21 3,2 Mon 11/15/2 Wed 11/17/2 2,3 Thu 11/18/2: Fri 11/19/21 6 Mon 11/22/2 Thu 11/25/2: 5,6 5 6 jack jack john 7 john 8Step by Step Solution
There are 3 Steps involved in it