Question: Before you can construct an activity-on-node Program Evaluation Review Technique (PERT) chart, you need to go through some preparatory work that includes which of the

Before you can construct an activity-on-node Program Evaluation Review Technique (PERT) chart, you need to go through some preparatory work that includes which of the following? You can list the best and worst care time duration for each task to help with further sensitivity analysis. List all of the resources needed for each task. Specify the priority for each task to help with possible sensitivity analysis. Specify the succeeding tasks for each task