Question: begin { tabular } { | l | l | l | l | l | } hline ACTIVITY & begin {

\begin{tabular}{|l|l|l|l|l|}
\hline ACTIVITY & \begin{tabular}{l}
PREDECESSO \\
\(\mathbf{R}\)
\end{tabular} & OPTIMISTIC & MOST LIKELY & PESSIMISTIC \\
\hline A & - & 3 & 4 & 5\\
\hline B & A & 2 & 3 & 4\\
\hline C & A & 4 & 5 & 6\\
\hline D & B & 4 & 4 & 4\\
\hline E & B & 2 & 5 & 6\\
\hline F & C,D,E & 2 & 4 & 5\\
\hline G & F & 2 & 4 & 6\\
\hline H & F & 4 & 6 & 7\\
\hline I & G, H & 4 & 6 & 8\\
\hline
\end{tabular}
NB: Time periods are in months.
A. Draw the activity network for this problem.
[10 marks]
B. Determine the Expected Time and Variance for each activity.
[10 marks]
C. Show the activity schedule (EST, EFT, LST, LFT) as well as slack. You may work in the network but please show the results in a table.
[12 marks]
D. Determine and state the critical path for this project. (This must be based on your work in c) and not by inspection.
[3 marks]
E. What are the expected time and the variance of the project?
[2 marks]
F. What is the probability the project will be finished within 30 months?
[3 marks]
(Total 30 marks)
\ begin { tabular } { | l | l | l | l | l | } \

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!