Question: begin{tabular}{ccc} hline Activity & Duration (days) & Predecessors hline A & 1.5 & None B & 3 & None C & 4.5

\begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 1.5 & None \\ B & 3 & None \\ C & 4.5 & A \\ D & 2.5 & A, B \\ E & 6 & C, D \\ F & 1 & D \\ G & 7 & E, F \\ \hline \end{tabular} a. Choose the correct project network diagram below. A. c. D