Question: begin{tabular}{|c|c|c|} hline Activity & Predecessor Activity & Duration (Weeks) hline A & & 3 hline B & A & 5 hline C

\begin{tabular}{|c|c|c|} \hline Activity &\begin{tabular}{|c|c|c|} \hline Activity &

\begin{tabular}{|c|c|c|} \hline Activity & Predecessor Activity & Duration (Weeks) \\ \hline A & & 3 \\ \hline B & A & 5 \\ \hline C & A & 7 \\ \hline D & B & 10 \\ \hline E & C & 5 \\ \hline F & D,E & 4 \\ \hline \end{tabular} For each of the following predecessor tables: - Draw a corresponding AON network. - Compute ES and EF for each activity. - Compute LS and LF for each activity. Find the critical path. - Determine the total slack and free slack