Question: Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to

Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be 81 units and there are three 8-hour shifts available each day to meet this production quota.

Task Req'd Time (in minutes) Predecessor
A 16 None
B 15 A
C 6 B
D 5 B
E 11 A
F 4 C, D
G 7 F
H 16 E
I 5 G, H

1, What is the takt time (in minutes) for this production line? (Round your answer to a one decimal place.)

2, What is the cycle time (in minutes) for this production line?

3, What is the combined idle time (in minutes) for this production line?

4, What is the overall efficiency for this production line? (answer as a percentage, and display your answer to two decimal places.) %

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!