Question: Below are the data for a Time - Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and

Below are the data for a Time-Cost CPM Scheduling model analysis.
The time is in days and the costs include both direct and indirect costs.
What are the total time of this project and total normal cost?
Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None 42 $ 200 $ 400
B A 43 $ 300 $ 600
C A 11 $ 200 $ 200
D B and C 32 $ 450 $ 550
E D 21 $ 500 $ 900
Total time is 9 days, total cost is $2650
Total time is 14 days, total cost is $1650
Correct!
Total time is 13 days, total cost is $1650
Total time is 12 days, total cost is $1700
Total time is 10 days, total cost is $1650Below are the data for a Time-Cost CPM Scheduling model analysis.
The time is in days and the costs include both direct and indirect costs.
What are the total time of this project and total normal cost?
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Normal],[Time]],\table[[Crash],[Time]],\table[[Normal],[Cost]],\table[[Crash],[Cost]]],[A,None,4,2,\table[[$
 Below are the data for a Time-Cost CPM Scheduling model analysis.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!