Question: Below are the data for a Time - Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and
Below are the data for a TimeCost CPM Scheduling model analysis.
The time is in days and the costs include both direct and indirect costs.
What are the total time of this project and total normal cost?
Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None $ $
B A $ $
C A $ $
D B and C $ $
E D $ $
Total time is days, total cost is $
Total time is days, total cost is $
Correct!
Total time is days, total cost is $
Total time is days, total cost is $
Total time is days, total cost is $Below are the data for a TimeCost CPM Scheduling model analysis.
The time is in days and the costs include both direct and indirect costs.
What are the total time of this project and total normal cost?
tableActivitytableImmediatePredecessortableNormalTimetableCrashTimetableNormalCosttableCrashCostANone,table$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock