Question: Below is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity
Below is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the network. Start E H End (a) Which is the CP? (b) Calculate the duration of the CP. (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time-units, what would be the impact on the project duration?
Step by Step Solution
3.41 Rating (170 Votes )
There are 3 Steps involved in it
The critical path is the longest path through the network which is ABDFGHJK b The duration of the cr... View full answer