Question: Below is a project that is due in 16 weeks. Activities and crash times are given below. What is the best schedule and cost? Please

Below is a project that is due in 16 weeks. Activities and crash times are given below. What is the best schedule and cost? Please explain in detail

Below is a project that is due in 16 weeks.

Below is a project that is due in 16 weeks.

Prec. Evt. Suc. Evt. Prec. Activ. Activity a b 1 1 1 2 3 4 4 5 6 d 2 3 4 5 5 5 6 7 7 TE (weeks) 3 6 8 7 5 10 4 5 6 none none none a b f h i d,e,f Additional Cost per Week Activity Crash Time (weeks) 7 6 2 3 f h I $40 20 10 30