Question: Below is an activity network with times (in weeks) shown above each node: image.png Which of the following statements is FALSE? Group of answer choices
Below is an activity network with times (in weeks) shown above each node: image.png Which of the following statements is FALSE? Group of answer choices The earliest start time for Activity A is zero since it is the first activity. The latest start time of Activity H is 21 weeks. The slack time Activity H is zero. The critical path is A-C-E-H