Question: Below is information about a BA 421 Market Study Project. Activity ID Activity Predecessor Responsibility Estimated Duration (Day) 1 Identify Target Customers Susan 5 2

Below is information about a BA 421 Market Study Project.

Activity ID Activity Predecessor Responsibility Estimated Duration (Day)
1 Identify Target Customers Susan 5
2 Develop Draft Questionnaire 1 Susan 10
3 Pilot-Test Questionnaire 2 Susan 20
4 Review Comments and Finalize Questionnaire 3 Susan 5
5 Prepare Mailing Labels 4 Steve 2
6 Print Questionnaire 4 Steve 10
7 Develop Data Analysis Software 4 Andy 12
8 Develop Software Test Data 4 Susan 2
9 Mail Questionnaire and Get Responses 5, 6 Steve 65
10 Test Software 7, 8 Andy 5
11 Input Response Date 9, 10 Jim 7
12 Analyze Results 11 Jim 8
13 Prepare Report 12 Jim 10
  1. Draw an activity-on-node (AON) network and copy into Word document or attach file. Please use the template AON_Template (1).xlsx Download AON_Template (1).xlsx. AON_Template.xlsx
  2. Identify the ES, EF, LS, LF, critical path, free slack and critical path. The Scheduling Project Exercise Excel file Lesson 3 Scheduling Project Exercise.docx(or found under Files) contains the format for entering this information. Once you enter this information, cut and paste the Excel table on your word document.

Actions

  1. Which of these tasks should the project manager track most closely?
  2. What would happen if a new estimate for Activity 5, Prepare Mailing Labels, increases its expected duration from two days to ten days? Would the project take longer? Would anything else change? Explain your answer.

PreviousNext

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!