Question: Below is information about a BA 421 Market Study Project. Activity ID Activity Predecessor Responsibility Estimated Duration (Day) 1 Identify Target Customers Susan 5 2
Below is information about a BA 421 Market Study Project.
| Activity ID | Activity | Predecessor | Responsibility | Estimated Duration (Day) |
|---|---|---|---|---|
| 1 | Identify Target Customers | Susan | 5 | |
| 2 | Develop Draft Questionnaire | 1 | Susan | 10 |
| 3 | Pilot-Test Questionnaire | 2 | Susan | 20 |
| 4 | Review Comments and Finalize Questionnaire | 3 | Susan | 5 |
| 5 | Prepare Mailing Labels | 4 | Steve | 2 |
| 6 | Print Questionnaire | 4 | Steve | 10 |
| 7 | Develop Data Analysis Software | 4 | Andy | 12 |
| 8 | Develop Software Test Data | 4 | Susan | 2 |
| 9 | Mail Questionnaire and Get Responses | 5, 6 | Steve | 65 |
| 10 | Test Software | 7, 8 | Andy | 5 |
| 11 | Input Response Date | 9, 10 | Jim | 7 |
| 12 | Analyze Results | 11 | Jim | 8 |
| 13 | Prepare Report | 12 | Jim | 10 |
- Draw an activity-on-node (AON) network and copy into Word document or attach file. Please use the template AON_Template (1).xlsx Download AON_Template (1).xlsx. AON_Template.xlsx
- Identify the ES, EF, LS, LF, critical path, free slack and critical path. The Scheduling Project Exercise Excel file Lesson 3 Scheduling Project Exercise.docx(or found under Files) contains the format for entering this information. Once you enter this information, cut and paste the Excel table on your word document.
Actions
- Which of these tasks should the project manager track most closely?
- What would happen if a new estimate for Activity 5, Prepare Mailing Labels, increases its expected duration from two days to ten days? Would the project take longer? Would anything else change? Explain your answer.
PreviousNext
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock