Question: Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices Act. ID Description Predecessor Optm. (a) Most
Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices
| Act. ID | Description | Predecessor | Optm. (a) | Most Likely (m) | Pess. (b) | Expected time |
| 1 | Design Package | None | 6 | 8 | 16 |
|
| 2 | Design Product | 1 | 8 | 12 | 13 |
|
| 3 | Build Package | 1 | 6 | 7 | 10 |
|
| 4 | Secure patent | 2 | 11 | 20 | 28 |
|
| 5 | Build product | 2 | 17 | 29 | 47 |
|
| 6 | Paint | 3,4,5 | 4 | 7 | 10 |
|
| 7 | Test market | 6 | 15 | 16 | 17 |
|
Calculate the expected time for all tasks and maintain one decimal place. Complete a critical path analysis. Complete forward and backward passes.
What is the critical path?
What is the project duration?
What is the latest start for Activity 4 "Secure patent?"?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts