Question: Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices Act. ID Description Predecessor Optm. (a) Most

Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices

Act. ID

Description

Predecessor

Optm. (a)

Most Likely (m)

Pess. (b)

Expected time

1

Design Package

None

6

8

16

2

Design Product

1

8

12

13

3

Build Package

1

6

7

10

4

Secure patent

2

11

20

28

5

Build product

2

17

29

47

6

Paint

3,4,5

4

7

10

7

Test market

6

15

16

17

Calculate the expected time for all tasks and maintain one decimal place. Complete a critical path analysis. Complete forward and backward passes.

What is the critical path?

What is the project duration?

What is the latest start for Activity 4 "Secure patent?"?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!