Question: Below is Part A ' s product structure with lead times in days.a ) What is the minimum planning horizon for part A ? b
Below is Part As product structure with lead times in days.a What is the minimum planning horizon for part Ab If the lead time for part G is reduced by would that result in any changes to the minimum planning horizon? If so what would be the change?