Question: Below shows a partially completed MPS record for ball bearings. Week Item: Ball bearing 1 2 3 4 5 6 7 8 9 1 0

Below shows a partially completed MPS record for ball bearings.
Week
Item: Ball bearing 12345678910
Forecast 550300400450300350200300450400
Orders 300350250250200150100100100100
Projected available balance
Available-to-promise
MPS 500
Quantitiy on-hand: 400 units
Lot Size: 500 units
Develop the MPS for ball bearings.