Question: Benchmarking-Rework Rework (Work Quality in%) = Work needing to be Reworked / Total Work in # or Hours Last year, a particular maintenance department had
Benchmarking-Rework
Rework (Work Quality in%) = Work needing to be Reworked / Total Work in # or Hours
Last year, a particular maintenance department had 2,322 of total work hours completed. Nobody likes rework due to poor quality.
What is the maximum number of those hours which could be rework if your organization needed to maintain a Quartile I standing?
Enter your answer as a decimal number of hours. For example, if you calculate two and a half hours as your answer, enter 2.5.