Question: Big Idea Critical Path Method Consider the critical path method example we did in class. How long will this project take if activity B required

Big Idea
Critical Path Method
Consider the critical path method example we did in class. How long will this project take if activity B required 5 days to complete, not 3?
Group of answer choices
26 days (B becomes critical if it takes more than 3 days to complete)
Not enough information
27 days (We add the additional days to the project duration)
25 days (B is not on the critical path)