Question: Big Idea Critical Path Method Consider the critical path method example we did in class. How long will this project take if activity B required
Big Idea
Critical Path Method
Consider the critical path method example we did in class. How long will this project take if activity B required days to complete, not
Group of answer choices
days B becomes critical if it takes more than days to complete
Not enough information
days We add the additional days to the project duration
days B is not on the critical path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
