Question: BITS 1213 - OPERATING SYSTEM ASSIGNMENT 2 (5%) QUESTION 1 (35 MARKS) a. Given the following jobs that are to be processed on a single

BITS 1213 - OPERATING SYSTEM ASSIGNMENT 2 (5%) QUESTION 1 (35 MARKS) a. Given the following jobs that are to be processed on a single processor: Table 1: Process Scheduling Process Arrival Time Service Time in ms in ms P1 0 5 P2 2 2 P3 4 9 P4 6 4 i. Illustrate a Gantt chart to show the schedules for Shortest Remaining Time (SRT) and Shortest Process Next (SPN) policies. Estimate the finish time, tumaround time, and normalized turnaround time for both algorithms. ii. (20 Marks)