Question: Black Bear Construction Company has a contract to construct a $6,000,000 bridge at an estimated cost of $5,300,000. The contract is to start in July
Black Bear Construction Company has a contract to construct a $6,000,000 bridge at an estimated cost of $5,300,000. The contract is to start in July 2017, and the bridge is to be completed in October 2019. The following data pertain to the construction period. 2017 2018 2019 Costs to date $1,325,000 $3,780,000 $5,430,000 Estimated costs to complete 3,975,000 1,620,000 Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000
What amount of gross profit should Black Bear recognize in 2018 using the percentage-of-completion method?
|
| A) $270,000 |
|
| B) $ 0 |
|
| C)$315,000 |
|
| D)$245,000 |