Question: **Blank One: (several input variables together vs. one input variable at a time) **Blank Two: (become negative vs. stay positive) **Blank Three: ($1.03 million, $1.93

**Blank One: (several input variables together vs. one input variable at a time)
**Blank Two: (become negative vs. stay positive)
**Blank Three: ($1.03 million, $1.93 million, $2.66 million, or $5.80 million)
**Blank Four: ($7.13, $6.56, $6.16, or $5.30)
6. Sensitivity and scenario analysis Different techniques for analyzing project risk require different input variables and assumptions. in the Suppose you are using the sensitivity analysis technique to evaluate project risk. You would change model to evaluate the effect of the input factors on the expected value. Mina is a risk analyst. She is conducting a sensitivity analysis to evaluate the riskiness of a new project that her company is considering investing in. Her risk analysis report includes the sensitivity curve shown on the graph. ? O Base Case NPV NPV (Millions of dollars) Base Case Cost of Capital 12 15 COST OF CAPITAL (Percent) if the cost of This curve implies that the project is not very sensitive to changes in cost of capital. The project's NPV is likely to capital increases to 15%. Along with the sensitivity analysis, Mina is including a scenario analysis for the project in her report, giving the probability of the project generating a negative NPV. Her report includes the following information about the scenario analysis: Data Collected Outcome NPV) -$3.50 million Pessimistic Most likely Probability (P) 0.20 0.45 $5.62 million Optimistic $11.34 million 0.35 Complete the missing information in Mina's report: The expected net present value of the project is Standard deviation of the net present value (the NPV of the project is likely to vary by) million
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts