Question: BLEM SOLVING. g the information given in the table, perform the following Draw the network diagram. (10 pts) Use Page 3 of your answer sheet.

BLEM SOLVING. g the information given in the

BLEM SOLVING. g the information given in the table, perform the following Draw the network diagram. (10 pts) Use Page 3 of your answer sheet. - Determine the expected duration of the project. (5 pts) Use Page 3 of your answer sheet. Identify the critical path. (5 pts) Use Page 3 of your answer sheet. Activity Normal time (days) 5 I 6 4 1-2 2-3 2-4 3-6 6-7 4-5 10 3 4-7 5-7 5 16 10