Question: Blossom Construction entered into a contract to construct a bridge for a contract price of $2.40 million. Construction began in 2019 and was completed in

Blossom Construction entered into a contract to construct a bridge for a contract price of $2.40 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract: 2019 2020 2021 Costs incurred during the year $623,000 $806,000 $675,900 Estimated costs to complete 1,377,000 571,000 0 Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places, e.g. 52.75% and other answers to 0 decimal places, e.g. 1,525.) 2019 2020 2021 Revenue $ $ $ Expenses Gross Profit $ $ $ ta $