Question: Bobs Warehouse is considering the following projects: Project Beta IRR(actual project return) X 1.6 19.8% Y 0.8 11% Z 0.9 16% Bobs Warehouse is an

Bobs Warehouse is considering the following projects:

Project

Beta

IRR(actual project return)

X

1.6

19.8%

Y

0.8

11%

Z

0.9

16%

Bobs Warehouse is an all-equity firm. The T-bill rate is 2.5%, and the expected return on the market is 14%. The firm has an equity beta =1. Which project(s) should the firm accept?

A.

Reject X, Accept Y, Accept Z

B.

Reject X, Reject Y, Accept Z

C.

Accept X, Reject Y, Reject Z

D.

Accept X, Reject Y, Accept Z