Question: BOM: Top Assembly (1 required) to Bracket ( 6 required) or Wood Screw (48 required) or Support Assembly (1 required) Center Support (1 required) or
BOM:
Top Assembly (1 required) to Bracket ( 6 required) or Wood Screw (48 required)
or
Support Assembly (1 required)
Center Support (1 required) or Side support (2 required)
| Table-Top Assembly | 8/1 | 8/8 | 8/15 | 8/22 | 8/29 | 9/5 | 9/12 | 9/19 | 9/26 | |
| Gross Requirements | ||||||||||
| Scheduled Receipts | 200 | |||||||||
| Projected On-Hand Inv. | 120 | |||||||||
| Net Requirements | ||||||||||
| Planned Order Receipts | ||||||||||
| Planned Order Releases | ||||||||||
| Lead Time (in weeks) | 2 | |||||||||
| Lot Size | 50 | |||||||||
For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19?
For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5?
Step by Step Solution
There are 3 Steps involved in it