Question: ( Bonus ) 3 . A system has two periodic tasks A ( 4 , 1 ) and B ( 6 , 2 ) ,

(Bonus)3. A system has two periodic tasks A (4,1) and B (6,2), and a deferrable server SD
(5,2). Two aperiodic jobs are released at 2 and 12 with execution time 3 and 2.5
respectively. Apply Earliest Deadline First algorithm to schedule periodic jobs.
a) Draw Gantt charts to illustrate the schedules of periodic and aperiodic jobs, as well as
the polling servers budget.
b) Calculate the response times for the two aperiodic jobs.