Question: both questions please QUESTION 21 Assume the earned value (EV) is 100 and actual cost (AC) is 200. What is the cost performance index? 50%
QUESTION 21 Assume the earned value (EV) is 100 and actual cost (AC) is 200. What is the cost performance index? 50% 100% None of these answers are correct 200% QUESTION 22 Please calculate the schedule performance index (SPD) given the following information Planned Value (PV) - 80: Earned Value (EV) - 100 80% 120% Unable to be determined 125%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
