Question: both questions please QUESTION 21 Assume the earned value (EV) is 100 and actual cost (AC) is 200. What is the cost performance index? 50%

both questions please
both questions please QUESTION 21 Assume the earned value (EV) is 100

QUESTION 21 Assume the earned value (EV) is 100 and actual cost (AC) is 200. What is the cost performance index? 50% 100% None of these answers are correct 200% QUESTION 22 Please calculate the schedule performance index (SPD) given the following information Planned Value (PV) - 80: Earned Value (EV) - 100 80% 120% Unable to be determined 125%