Question: Bracket Manufacturing uses a Kanban system for a component. Daily demand is 1 , 1 0 0 units. Each container has a combined waiting and

Bracket Manufacturing uses a Kanban system for a component.
Daily demand is 1,100 units. Each container has a combined
waiting and processing time of 0.65 days. If the container size is
100 and the alpha value (a) is 12%, how many Kanban card sets
should be authorized? Round your answer up to the whole
number.
Kanban card set(s)
What is the maximum authorized inventory? Use the rounded
value from the previous question. Round your answer to the
nearest whole number.
unit(s)