Question: Brianna is a software developer who has four programs to complete this sea on. She estimates that one program will take two weeks to complete,
Brianna is a software developer who has four programs to complete this sea on. She estimates that one program will take two weeks to complete, two of them will take three weeks to complete and the other one will take her four weeks. Brianna plans to use some of her vacation time this season, so she will not accept any more program requests beyond these four this season. What is Briannas flow rate, or projects per week, during the time these programs are worked on?