Question: Brief Exercise 1 1 - 7 Computing Fixed Overhead Variances ( LO 2 - CC 1 1 , 1 2 ) LatAm Inc. has a
Brief Exercise Computing Fixed Overhead Variances LO CC
LatAm Inc. has a standard costing system in which it applies overhead to products on the basis of the standard direct labourhours
allowed for the actual output of the period. Data concerning the most recent year appear below:
Required:
Compute the fixed portion of the predetermined overhead rate for the year.
Compute the fixed overhead budget variance and volume variance. Indicate the effect of each variance by selecting F for
favourable, U for unfavourable, and "None" for no effect ie zero variance