Question: Brief Exercise 170 Cyber Construction's manufacturing costs for August when production was 1,000 units appear below: Direct material$12 per unit Direct labor$7,500 Variable overhead6,000 Factory

Brief Exercise 170

Cyber Construction's manufacturing costs for August when production was 1,000 units appear below:

Direct material$12 per unit

Direct labor$7,500

Variable overhead6,000

Factory depreciation9,000

Factory supervisory salaries7,800

Other fixed factory costs2,500

Compute the flexible budget manufacturing cost amount for a month when 900 units are produced.

Flexible Budget Manufacturing Cost $