Question: Brief Exercise 23-4 Your answer is partially correct. Try again Simba Company's standard materials cost per unit of output is $9.68 (2.20 pounds x $4.40).

Brief Exercise 23-4 Your answer is partially correct. Try again Simba Company's standard materials cost per unit of output is $9.68 (2.20 pounds x $4.40). During July, the company purchases and uses 2,662 pounds of materials costing $14,375 in making 1,100 units of finished product. Compute the total, price, and quantity materials variances. (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to O decimal places, e.g. 52.) Total materials variance Unfavorable Materials price variance Unfavorable Materials quantity variance Unfavorable
Step by Step Solution
There are 3 Steps involved in it