Question: Brighten Company applied overhead using machine hours as the allocation base, at a rate of $16 per machine hour. Job 324 requires $620 worth of
Brighten Company applied overhead using machine hours as the allocation base, at a rate of $16 per machine hour. Job 324 requires $620 worth of material, 7 hours of labor at $18 per hour and 10 machine hours. What is the cost of job 324? A. $776 B. $888 C. $126 D. $936