Question: Bronze Company had the following information: Activity Driver Unit Variable Cost Level of Activity Driver Units sold $ 30 -- Setups 1,200 60 Engineering hours
Bronze Company had the following information:
| Activity Driver | Unit Variable Cost | Level of Activity Driver |
| Units sold | $ 30 | -- |
| Setups | 1,200 | 60 |
| Engineering hours | 40 | 1,000 |
| Other data: | ||
| Total fixed costs (traditional) | $500,000 | |
| Total fixed costs (Activity-based costing) | 200,000 | |
| Unit selling price | 50 |
What is the break-even point in units using activity-based costing (ABC)?
| 40,100 units | |
| 31,500 units | |
| 15,600 units | |
| 20,300 units |