 Brown Bag Eco-Store is considering a project with an initial cash

Brown Bag Eco-Store is considering a project with an initial cash outlay of Php 80,000 and an expected free cash flows of Php 30,000 at the end of each year for 4 years. The required rate of return for this project is 10%. What is the project's net present value