Brown's Machining has three jobs with the routings and processing times(in minutes)as indicated on its drill press,
Fantastic news! We've Found the answer you've been seeking!
Question:
Brown's Machining has three jobs with the routings and processing times (in minutes) as indicated on its drill press, lathe, milling machine, and grinder. It uses an LWR dispatching rule.
Job 1: D(15), L(25), G(45)
Job 2: D(20, M(25), G(30)
Job 3: G(25), L(25), D(15), M(15)
What time is Job 3 completed?