Question: B.SU egi % Cooperational project D.timely project A BP DS 2 4 FI G HP C 10. In the network diagram above, what would be

B.SU egi % Cooperational project D.timely project

B.SU egi % Cooperational project D.timely project A BP DS 2 4 FI G HP C 10. In the network diagram above, what would be the critical path if the duration of activity C increased from 8 to 10? A. ABGHIF B. ABGHIF & ABDEF C. ABCEF D. ABCF 51