Question: Budget cost per week A 0 2 0 2 0 11000 Budgeted total cost B 2 5 2 5 0 13000 C 2 6 5
Budget cost per week
| A | 0 | 2 | 0 | 2 | 0 | 11000 | Budgeted total cost | |||||||||
| B | 2 | 5 | 2 | 5 | 0 | 13000 | ||||||||||
| C | 2 | 6 | 5 | 9 | 3 | 12000 | ||||||||||
| D | 5 | 8.83 | 5 | 8.83 | 0 | 10000 | ||||||||||
| E | 8.83 | 11.83 | 8.83 | 11.83 | 0 | 11000 | ||||||||||
| F | 6 | 10.83 | 9 | 13.83 | 3 | 15000 | ||||||||||
| G | 11.83 | 13.83 | 11.83 | 13.83 | 0 | 9000 | ||||||||||
| H | 13.83 | 16.83 | 13.83 | 16.83 | 0 | 10000 | ||||||||||
What calculation is used to figure the budgeted total cost?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts