Question: Budget Performance Reports for Cost Centers Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow: Plant Actual Budget Over
Budget Performance Reports for Cost Centers
Partially completed budget performance reports for Delmar Company, a manufacturer of light duty motors, follow:
| Plant | Actual | Budget | Over Budget | (Under) Budget | |
|---|---|---|---|---|---|
| Eastern Region | $410,500 | $410,500 | $0 | ||
| Central Region | 292,600 | 295,600 | (3,000) | ||
| Western Region | (g) | (h) | (i) | ||
| $(j) | $(k) | $(l) | $(3,000) |
| Department | Actual | Budget | Over Budget | (Under) Budget |
|---|---|---|---|---|
| Chip Fabrication | $(a) | $(b) | $(c) | |
| Electronic Assembly | 76,000 | 75,020 | 980 | |
| Final Assembly | 118,330 | 119,280 | $(950) | |
| $(d) | $(e) | $(f) | $(950) |
| Cost | Actual | Budget | Over Budget | (Under) Budget |
|---|---|---|---|---|
| Factory wages | $25,010 | $23,370 | $1,640 | |
| Materials | 58,240 | 58,650 | $(410) | |
| Power and light | 4,880 | 4,100 | 780 | |
| Maintenance | 6,880 | 6,280 | 600 | |
| $95,010 | $92,400 | $3,020 | $(410) |
a. Complete the budget performance reports by determining the correct amounts for the lettered spaces (a-l) as marked above.
| Amount | Amount |
|---|---|
| a. $fill in the blank 1 | g. $fill in the blank 2 |
| b. $fill in the blank 3 | h. $fill in the blank 4 |
| c. $fill in the blank 5 | i. $fill in the blank 6 |
| d. $fill in the blank 7 | j. $fill in the blank 8 |
| e. $fill in the blank 9 | k. $fill in the blank 10 |
| f. $fill in the blank 11 | l. $fill in the blank 12 |
b. Complete the following memo to Randi Wilkes, vice president of production for Delmar Company, explaining the performance of the production division for June.
MEMO To: Randi Wilkes, Vice President of Production
The fill in the blank 1 of 4
Eastern RegionCentral RegionWestern Region
plant has experienced a budget overrun. Its budget reveals that the fill in the blank 2 of 4
Chip FabricationElectronic AssemblyFinal Assembly
Department caused the majority of the budget overrun. The supervisor of the fill in the blank 3 of 4
Chip FabricationElectronic AssemblyFinal Assembly
Department should investigate the reasons for the budget overruns in fill in the blank 4 of 4
factory wages, materials, and maintenancematerials, power and light, and maintenancefactory wages, power and light, and maintenance
.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts