Question: BUDGET UNIT TOTAL $ $ PRODUCTION (8,700 units) Materials 4 kg @ $4.50/kg 18 156,600 Labour 5hrs @ $5/hr 25 217,500 ACTUAL $ Production (8,900
| BUDGET | UNIT | TOTAL | |
| $ | $ | ||
| PRODUCTION | (8,700 units) | ||
| Materials | 4 kg @ $4.50/kg | 18 | 156,600 |
| Labour | 5hrs @ $5/hr | 25 | 217,500 |
| ACTUAL | $ | |
| Production | (8,900 units) | |
| Materials | purchased 35,464 kgs for $163,455 (used 34,928 kgs) | 161,043 |
| Labour | (45,400 hours worked and paid) | 224,515 |
Required: Calculate the following variances:
(i) Total Materials Variance
(ii) Materials Usage Variance
(iii) Materials Price Variance
(iv) Total Labour Variance
(v) Labour Efficiency Variance
(vi) Labour Rate Variance
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
